i have a question , there is a project it has been planned for some dates say that as baseline one. and after some duration of the progress the project has been rescheduled by keeping actuals upto data date same and new planned dates is continued from the data date. so now it became our baseline two. now i have to see on the screen base line one (start, finish dates)base line two( start, finish dates) and (actual start and actual finish) can you give me procedure for this in P3 and P6