Multiple Critical Paths P6 In MSP I set a deadline date on milestones and it would display a critical path to each, is there a way to replicate this in P6?
The standard Multiple critical path setting in the advanced tab of Scheduling options is not what I am looking for, I need to display a separate critical path for each milestone I select in my schedule, this would be representing different work streams.